Implementation - 3.4 Resources to be committed

Instructions

This chapter consists of two tables. The first is the listing of effort per partner divided between different work packages.

Make sure that the partner efforts are appropriately balanced and in line with their role in the project. A partner in a supporting role should not have as many person months as a partner that acts as the leading technology developer.

The second is a justification of other costs, that need to be itemised if they are greater than 15% of the personnel costs of the individual partner organisation.

You should give a short yet clear justification of why a specific cost item is needed, how much it costs, and to which Work Package (and task, if possible) the cost relates to.

Example

Table 3.4a: Summary of staff effort

 

WP 1

WP 2

WP 3

WP 4

WP 5

WP 6

Total PMs

1 – COMPANY A

40

12

26

35

16

4

133

2 – COMPANY B

4

58

28

19

8

2

119

3 – UNIVERSITY A

2

3

17

0

10

3

35

4 – PILOT PARTNER A

0

0

3

86

12

2

103

Etc…

 

 

 

 

 

 

 

Total PMs/Work Package

46

73

74

140

46

11

390

 

Resources

1 – COMPANY A

Cost (€)

Justification

Travel

40 000

Estimated 7 consortium meetings (2ppl/meeting, WP6), 2 review meetings (1person/meeting, WP6) and 8 technology development meetings (2-3 ppl/meeting, WPs 1 & 3). Average 1000€/trip. Total 40 000 €

Equipment

80 000

Sensor test signal generator. Depreciated over five years. 20 000 €/ year for each project year (WP1)

Other goods and services

120 000

Consumables for prototype sensor network development, including chips, circuit boards, casings, etc. 100 000 € (WP1)

Communicationl material, such as leaflets, web page design, etc. 15 000 € (WP 5)

Costs for audit at the end of project. 5 000 € (WP 6)

Total

240 000

 

 